Project Delivery Method: Project Budget: Construction Duration: Funding Source: |
Design/Build $9.2 million December 2012 - September 2013 Proposition N
|
| |
| Scope/Summary |
|
The new Miramar College Administration Building project will provide for 17,000 gross square feet of new construction at the north end of the campus, and allow for the existing administration wing to be converted to a classroom facility to support the expansion of San Diego Continuing Education programs offered at Miramar.
The first floor of the new facility will house the reprographics, mailroom, and stockroom/receiving functions in addition to the office of the Vice President of Administrative Services (VPA). The second floor will house offices for the college President, Vice President of Instruction (VPI) and Vice President of Student Services (VPSS) in addition to two conference rooms and an outdoor patio area. This project is slated to achieve a Leadership in Energy and Environmental Design (LEED) Silver certification.
|
| Project Team: |
- Architect: IBI Group
- Builder: Charles Pankow Builders, Ltd.
- Mechanical Engineers: Southland Industries
- Electrical Engineer: SASCO Electric
- Civil Engineer: Snipes-Dye Associates
- Structural Engineer: KPFF Consulting Engineers
- Landscape Architect: Wimmer Yamada & Caughey
- Propositions S and N Program Manager: Gafcon, Inc.
- Campus Project Manager: James Bray, Gafcon, Inc.
- Project Manager: Tyler Campbell, EIT, LEED® GA, Gafcon, Inc.
- Furniture, Fixture & Equipment (FF&E) Project Manager: Laura Faustine, Gafcon, Inc.
| |
|
|
|
|
|
|
|
|
|
|