Project Delivery Method: Project Budget: Construction Duration: Funding Source:
|
Design-Bid-Build (Agency CM) $9.7 million 2008 - 2010 Proposition S |
| |
| Scope/Summary |
|
The Infrastructure Phase I project consists of renovated new surface parking lots, road improvements, utility support to future buildings, new sidewalks and landscaping over a majority of the campus.
|
| By the numbers: |
- 18.3 Miles or 98,589 linear feet of irrigation pipe buried in the ground ranging in size from 6-inch diameter down to 3/4-inch diameter
- 7,800 pop-up sprinkler heads
- 21,457 square feet of drip irrigation in appropriate areas to minimize water use
- 763 newly planted trees (24' box, 36' box and 60' box sizes)
- 63,770 newly planted shrubs, ornamental grasses and ground covers
- 149,561 square feet of newly created turf areas
- 51,794 square feet of native plant buffer adjacent to the environmentally sensitive area on the northwest portion of the site
|
| Project Team: |
- Architect: Wimmer Yamada & Caughey
- Contractors: West Coast General Corporation
- Mechanical Engineer: MA Engineering
- Electrical Engineer: LSW Engineers California Inc. (Electrical Design)
- Civil Engineer: R.B.F. Consulting
- Landscape Architect: Wimmer Yamada and Caughey
- Propositions S and N Program Manager: Gafcon, Inc.
- Campus Project Manager: James Bray, Gafcon, Inc.
- Project Manager: Charlotte Zolezzi, Gafcon, Inc.
| |
|
|
| Edit in Browser | /_layouts/images/icxddoc.gif | /Projects/Miramar/_layouts/formserver.aspx?XsnLocation={ItemUrl}&OpenIn=Browser | 0x0 | 0x1 | FileType | xsn | 255 | | Edit in Browser | /_layouts/images/icxddoc.gif | /Projects/Miramar/_layouts/formserver.aspx?XmlLocation={ItemUrl}&OpenIn=Browser | 0x0 | 0x1 | ProgId | InfoPath.Document | 255 | | Edit in Browser | /_layouts/images/icxddoc.gif | /Projects/Miramar/_layouts/formserver.aspx?XmlLocation={ItemUrl}&OpenIn=Browser | 0x0 | 0x1 | ProgId | InfoPath.Document.2 | 255 | | Edit in Browser | /_layouts/images/icxddoc.gif | /Projects/Miramar/_layouts/formserver.aspx?XmlLocation={ItemUrl}&OpenIn=Browser | 0x0 | 0x1 | ProgId | InfoPath.Document.3 | 255 | | Edit in Browser | /_layouts/images/icxddoc.gif | /Projects/Miramar/_layouts/formserver.aspx?XmlLocation={ItemUrl}&OpenIn=Browser | 0x0 | 0x1 | ProgId | InfoPath.Document.4 | 255 | | View in Web Browser | /_layouts/images/ichtmxls.gif | /Projects/Miramar/_layouts/xlviewer.aspx?listguid={ListId}&itemid={ItemId}&DefaultItemOpen=1 | 0x0 | 0x1 | FileType | xlsx | 255 | | View in Web Browser | /_layouts/images/ichtmxls.gif | /Projects/Miramar/_layouts/xlviewer.aspx?listguid={ListId}&itemid={ItemId}&DefaultItemOpen=1 | 0x0 | 0x1 | FileType | xlsb | 255 | | Snapshot in Excel | /_layouts/images/ewr134.gif | /Projects/Miramar/_layouts/xlviewer.aspx?listguid={ListId}&itemid={ItemId}&Snapshot=1 | 0x0 | 0x1 | FileType | xlsx | 256 | | Snapshot in Excel | /_layouts/images/ewr134.gif | /Projects/Miramar/_layouts/xlviewer.aspx?listguid={ListId}&itemid={ItemId}&Snapshot=1 | 0x0 | 0x1 | FileType | xlsb | 256 |
|
|
|
|
|
|
|
|
|
|
|