Mesa College Project Sites
 

 12600 - I-300 Building Demolition

Project Delivery Method:
Project Budget:

Construction Duration:

T.B.D.
$12.8 million
2014-2015

 
Scope/Summary

The remodel building project is scheduled to be completed by the spring of 2015. This building is part of the Fine Arts/ Dramatic Arts Building renovation and remodeling project.

 

Project Team:

  • Campus Project Manager: Diane K. Malone, AIA NCARB LEED AP, Gafcon, Inc.