Program Status
Design/Construction
Propositions S&N
Projects
Programs
Contractors
Construction Bond Program
Construction Bond Program > Program Status > Pages > program.aspx  

Program Status
 

 Project Performance Measures

Expand/Collapse Campus : City College ‎(18)
11110Use SHIFT+ENTER to open the menu (new window).
Arts & Humanities Building (Construct Humanities Building)Going WellGoing WellGoing Well
11140Use SHIFT+ENTER to open the menu (new window).
Land Acquisition - Vocational TechnologyProject CompleteProject CompleteProject Complete
11150Use SHIFT+ENTER to open the menu (new window).
Campus Site Design & Env ReviewProject CompleteProject CompleteProject Complete
11210Use SHIFT+ENTER to open the menu (new window).
Construct Child Development CenterGoing WellGoing WellGoing Well
11220Use SHIFT+ENTER to open the menu (new window).
Career Technology Center (Vocational Tech Center)Project CompleteProject CompleteProject Complete
11240Use SHIFT+ENTER to open the menu (new window).
Business Technology BuildingGoing WellGoing WellGoing Well
11250Use SHIFT+ENTER to open the menu (new window).
Engineering Technology BuildingGoing WellGoing WellGoing Well
11260Use SHIFT+ENTER to open the menu (new window).
Science BuildingGoing WellGoing WellGoing Well
11310Use SHIFT+ENTER to open the menu (new window).
Repair and Renovate "M" BuildingGoing WellGoing WellGoing Well
11320Use SHIFT+ENTER to open the menu (new window).
"D" Building RoofGoing WellGoing WellGoing Well
11330Use SHIFT+ENTER to open the menu (new window).
"A" Building RenovationScheduledScheduledScheduled
11340Use SHIFT+ENTER to open the menu (new window).
"C" Building Classrooms - Lang/Speech/Visual ArtsScheduledScheduledScheduled
11410Use SHIFT+ENTER to open the menu (new window).
Renovate "L" BuildingProject CompletedProject CompletedProject Completed
11420Use SHIFT+ENTER to open the menu (new window).
Renovate "P" BuildingProject CompleteProject CompleteProject Complete
11430Use SHIFT+ENTER to open the menu (new window).
Infrastructure Upgrade Across CampusThe initial Infrastructure budget did not have adequate funding to provide and install everything that needs to be provided and installed.Going WellGoing Well
11710Use SHIFT+ENTER to open the menu (new window).
Construct "R" Building ClassroomProject CompleteProject CompleteProject Complete
11720Use SHIFT+ENTER to open the menu (new window).
Modular VillageProject CompleteProject CompleteProject Complete
11810Use SHIFT+ENTER to open the menu (new window).
Land Acq + Gen Purpose Classroom BldgGoing WellGoing WellGoing Well
Expand/Collapse Campus : Continuing Education ‎(10)
14110Use SHIFT+ENTER to open the menu (new window).
ECC Land Acq. and Reloc. Skills CenterProject CompleteProject CompleteProject Complete
14120Use SHIFT+ENTER to open the menu (new window).
Clairemont/Linda Vista Campus BldgGoing WellGoing WellGoing Well
14210Use SHIFT+ENTER to open the menu (new window).
North CityGoing WellGoing WellGoing Well
14220Use SHIFT+ENTER to open the menu (new window).
ECC Phase IIB WingGoing WellGoing WellGoing Well
14310Use SHIFT+ENTER to open the menu (new window).
West Citty Center/Point Loma CampusProject CompleteProject CompleteProject Complete
14420Use SHIFT+ENTER to open the menu (new window).
Consolidation of Centre City and CCCGoing WellGoing WellGoing Well
14520Use SHIFT+ENTER to open the menu (new window).
Seismic Retrofit - Secondary EffectsProject CompleteProject CompleteProject Complete
14610Use SHIFT+ENTER to open the menu (new window).
Mid City CenterProject CompleteProject CompleteProject Complete
14710Use SHIFT+ENTER to open the menu (new window).
Land Acquisition & Renovation of DSCGoing WellGoing WellGoing Well
14810Use SHIFT+ENTER to open the menu (new window).
Computer Hardware & SoftwareGoing WellGoing WellGoing Well
Expand/Collapse Campus : Mesa College ‎(20)
12110Use SHIFT+ENTER to open the menu (new window).
Math and Science BuildingGoing WellGoing WellGoing Well
12120Use SHIFT+ENTER to open the menu (new window).
Instructional Technology BuildingGoing WellScheduledScheduled
12130Use SHIFT+ENTER to open the menu (new window).
Allied Health BuildingProject CompleteProject CompleteProject Complete
12140Use SHIFT+ENTER to open the menu (new window).
Campus Site Design & Env ReviewScheduledConcernScheduled
12210Use SHIFT+ENTER to open the menu (new window).
East Campus Improvement ProjectScheduleScheduleSchedule
12220Use SHIFT+ENTER to open the menu (new window).
Stockroom & Facilities Support AreaGoing WellScheduledScheduled
12250Use SHIFT+ENTER to open the menu (new window).
Renovate Visual Arts ProgramProject CompleteProject CompleteProject Complete
12310Use SHIFT+ENTER to open the menu (new window).
Infrastructure - Fire/Util/OtherGoing WellGoing WellGoing Well
12320Use SHIFT+ENTER to open the menu (new window).
Humanities, Languages & MulticulturalProject CompletedProject CompletedProject Completed
12410Use SHIFT+ENTER to open the menu (new window).
Repair Student Services FacilitySerious ConcernSerious ConcernSerious Concern
12420Use SHIFT+ENTER to open the menu (new window).
Cafeteria/Bookstore/StockroomGoing WellScheduledScheduled
12450Use SHIFT+ENTER to open the menu (new window).
Cogeneration FacilityProject CompletedProject CompletedProject Completed
12510Use SHIFT+ENTER to open the menu (new window).
Muir Property AcquisitionProject CompletedProject CompletedProject Completed
12520Use SHIFT+ENTER to open the menu (new window).
Fine Arts & Dramatic Arts FacilitiesGoing WellScheduledScheduled
12530Use SHIFT+ENTER to open the menu (new window).
Temporary Parking/All Weather TrackProject CompleteSerious ConcernProject Complete
12540Use SHIFT+ENTER to open the menu (new window).
Modular VillageProject CompleteProject CompleteProject Complete
12550Use SHIFT+ENTER to open the menu (new window).
Design CenterProject CompleteProject CompleteProject Complete
12600Use SHIFT+ENTER to open the menu (new window).
I-300 Building RenovationGoing WellScheduledScheduled
12721Use SHIFT+ENTER to open the menu (new window).
Social Behavioral ScienceGoing WellGoing WellGoing Well
12722Use SHIFT+ENTER to open the menu (new window).
Fitness CenterGoing WellScheduledScheduled
Expand/Collapse Campus : Miramar College ‎(27)
13110Use SHIFT+ENTER to open the menu (new window).
Library/Learning Resource Center/PIOGoing WellGoing WellGoing Well
13120Use SHIFT+ENTER to open the menu (new window).
Science & Technology BuildingProject CompletedProject CompletedProject Completed
13130Use SHIFT+ENTER to open the menu (new window).
Automotive Technology Career Instructional BuildingProject CompletedProject CompletedProject Completed
13140Use SHIFT+ENTER to open the menu (new window).
Mathematics & Business Building (Construct Technology Building)Going WellGoing WellGoing Well
13150Use SHIFT+ENTER to open the menu (new window).
Arts & Humanities BuildingGoing WellGoing WellGoing Well
13160Use SHIFT+ENTER to open the menu (new window).
Campus Site Design & Environmental ReviewProject CompletedProject CompletedProject Completed
13170Use SHIFT+ENTER to open the menu (new window).
Public Safety Driving RangeScheduledScheduledScheduled
13180Use SHIFT+ENTER to open the menu (new window).
EVOC Driving Course (Public Safety Training Center)Going WellGoing WellGoing Well
13210Use SHIFT+ENTER to open the menu (new window).
Hourglass Park FieldhouseProject CompletedProject CompletedProject Completed
13220Use SHIFT+ENTER to open the menu (new window).
Student Services Center (Temp Library)ScheduledScheduledScheduled
13230Use SHIFT+ENTER to open the menu (new window).
Computing & Distribution CenterProject CompletedProject CompletedProject Completed
13240Use SHIFT+ENTER to open the menu (new window).
Cafeteria/Bookstore & Student/CampusGoing WellGoing WellGoing Well
13250Use SHIFT+ENTER to open the menu (new window).
Cogeneration FacilityProject CompletedProject CompletedProject Completed
13310Use SHIFT+ENTER to open the menu (new window).
Repair/Renovate Science BuildingScheduledScheduledScheduled
13410Use SHIFT+ENTER to open the menu (new window).
Expand Automotive Tech Career BldgGoing WellGoing WellGoing Well
13420Use SHIFT+ENTER to open the menu (new window).
Aviation Maintenance Tech Center R/RGoing WellGoing WellGoing Well
13430Use SHIFT+ENTER to open the menu (new window).
Advanced Transportation Tech CtrGoing WellGoing WellGoing Well
13511Use SHIFT+ENTER to open the menu (new window).
Infrastructure - Phase IGoing WellGoing WellGoing Well
13520Use SHIFT+ENTER to open the menu (new window).
Construct "Leave A Legacy Plaza"Project CompleteProject CompleteProject Complete
13530Use SHIFT+ENTER to open the menu (new window).
Boiler ExpansionProject CompleteProject CompleteProject Complete
13540Use SHIFT+ENTER to open the menu (new window).
Parking Structure #1 & Police SubstationGoing WellGoing WellGoing Well
13500Use SHIFT+ENTER to open the menu (new window).
Campus Safety EnhancementsScheduledScheduledScheduled
13560Use SHIFT+ENTER to open the menu (new window).
Infrastructure - Phase IIGoing WellGoing WellGoing Well
13610Use SHIFT+ENTER to open the menu (new window).
Arts VillageProject CompleteProject CompleteProject Complete
13620Use SHIFT+ENTER to open the menu (new window).
Reprographic/Mailroom RelocationProject CompletedProject CompletedProject Completed
13630Use SHIFT+ENTER to open the menu (new window).
College Service Center & Police/Emergency ServicesScheduledScheduledScheduled
13650Use SHIFT+ENTER to open the menu (new window).
Maintenance Facility ExpansionScheduledScheduledScheduled

 Program Status Legend

 
Serious Concern
Concern
Going Well
Project Complete